Measuring and Digging the Subtropical Swimming Pool

I measured and excavated the hole for my DIY subtropical swimming pool garden, renting machinery and installing retaining sheets over two days.

By RobbertPosted

Mini subtropisch zwemparadijs deel 2 (uitmeten en graven) zelfbouw/diy

Playing loads the video from YouTube.

938 views on YouTube · Open on YouTube (Robbert DIY projects)

In this second part of my subtropical garden renovation, I focus on laying out and digging the hole for the swimming pool. After shoring up the fence in the first part, I now mark the exact dimensions needed for the 3-meter pool, the perimeter insulation, and the surrounding concrete structure.

To save time and hard labor, I rent excavation machinery and work alongside help to dig out the pit. Over two days of heavy work, we install retaining sheets, clear out 11 trailers of sand, and successfully shape the 14-cubic-meter hole ready for the next phase.

Steps

  1. Step 1: Measuring and marking the pool and veranda layout

    I start by measuring the ground to determine where the hole must be dug and where the flat foundation will lie. I also mark where the veranda will stand using square rubber tiles that measure exactly 3 by 3 meters. The pool hole must be at least 340 by 340 centimeters to fit a 3-meter pool in the middle, leaving 20 centimeters on each side for perimeter insulation and the outer concrete basin. I use red spray paint to mark the excavation boundaries.

    The hole overlaps with the veranda area. Later in the project, the slanted poles of the veranda can be moved half a meter backward so the motorized rolling pool cover can retract under the veranda without hitting the poles. Beams marked with red dots indicate where the fence poles are in the ground. Between these red dots, I need to dig straight down. Outside of these lines, I do not need to dig, so I can let it slope slightly.

    Because the pool is round, we do not need to dig out the corners. These support beams stay on solid ground and continue to support the fence weight even though everything underneath is excavated.

    What I used

    ItemAmountNotes
    red spray paint1used to mark excavation lines
    square rubber tilesseveralused to measure the 3 by 3 meter veranda area
  2. Step 2: Renting machinery and clearing stones

    With the help of two people, we clear the space completely from small stones so it is ready for digging. Digging this by hand would be too much hard work, so we rent small machines from Jansen in Beik. The machines work great and make the work go extremely fast.

    What I used

    ItemAmountNotes
    excavation machinery1rented from Jansen in Beik
  3. Step 3: Installing betonplex sheets and digging on the second day

    We show a large pit and another pole set in the ground. Next to this pole, we screw betonplex sheets against it to hold back the sand and prevent it from shifting. Today is the second day of digging, and both betonplex sheets are installed on this side while the back is filled with yellow sand.

    Today we dig the corners a bit deeper so they also reach a depth of 1.20 meters. This allows the remaining sheet to be put in place so the ground stays firm. Afterward, we excavate the rest of the pool area behind me.

    What I used

    ItemAmountNotes
    betonplex sheetsmultiplescrewed against poles to hold back sand
    yellow sandseveral loadsused to fill the back
  4. Step 4: Hauling away sand and finishing the excavation

    We have now hauled away six trailer loads of sand and need about four more. After two days of intensely hard work, we have removed 11 trailer loads of sand in total, which equals about 14 cubic meters of sand. It was heavy labor, but the hole is finally dug.

    What I used

    ItemAmountNotes
    trailers11used to haul away sand
  5. Step 5: Takeaways

    • Leave 20 centimeters on each side of the pool for perimeter insulation and the outer concrete shell.

    • Leave the corner poles on solid ground so they can support the fence weight while digging underneath.

    • Renting machinery from Jansen in Beik saves a tremendous amount of manual labor.

    • Use betonplex sheets to prevent sand from shifting and sliding into the excavation.

    • We removed 11 trailer loads of sand totaling about 14 cubic meters.

Everything I used

ItemAmountNotes
red spray paint1used to mark excavation lines
square rubber tilesseveralused to measure the 3 by 3 meter veranda area
excavation machinery1rented from Jansen in Beik
betonplex sheetsmultiplescrewed against poles to hold back sand
yellow sandseveral loadsused to fill the back
trailers11used to haul away sand

Next Steps

The excavation is complete and the pit is ready. In the next episode, we will build the formwork and pour the foundation so it can cure.