Welcome to part three of building my mini subtropical swimming paradise. In this part, I show how the foundation for the pool is poured and how the steel wall and frame are installed using a Bestway Hydrium 300cm steel wall pool as a formwork.
Work is kept dry and comfortable under a tent and sail. After pouring almost two tons of concrete and letting it cure, I assemble the steel pool frame inside the pit and seal the edges to prepare for pouring liquid concrete insulation later.
Steps
Step 1: Reviewing the plan and preparing the workspace
Welcome to part three of building my subtropical swimming paradise. In previous parts, I dug a hole that is 3.40 meters across and 1.20 meters deep. I share the master plan through an animation showing the pool, artificial plants, bamboo, wooden verandas, solar heaters on the roof, a tiki bar, and a possible large water slide.
To stay dry and warm while working, I have stretched a sail over the garden and set up a tent.
Step 2: Preparing the foundation site with wood and stakes
Almost two tons of concrete bags have arrived for the foundation plate. I laid thick 6cm wooden planks over the edges of the pool so there is no point load on the ground that could cause the hole to collapse, and my pool ladder is already coming in handy. I placed stakes around the 3.40-meter wide hole and set them all exactly 10cm high so the poured concrete will be completely level.
What I used
Item Amount Notes concrete bags almost two tons for the foundation plate wooden planks thick 6cm thick, placed over the edges to prevent point load stakes multiple set at exactly 10cm height for level pouring pool ladder 1 already coming in handy Step 3: Placing reinforcement and pouring the concrete foundation
On a new day, I placed the liner in the pool and put reinforcement all around the bath so the sides and steel crate will bond well with the foundation plate. With the mold ready, I mixed and poured the concrete. After 24 hours, the concrete is hard enough to walk on, and I used a brick to smooth down a high spot and make it flat.
Concrete takes 24 hours to let you walk on it, and 7 days to reach full strength, but we are not waiting that long to continue.
What I used
Item Amount Notes liner 1 placed in the pool reinforcement around the bath for good adhesion brick 1 used to smooth high spots on the concrete Step 4: Assembling the pool frame and steel wall
I measured the center of the hardened concrete and started laying out the blue bottom rails and brackets to build the frame. I am using a Bestway Hydrium 300cm steel wall pool. Working in the 1.20-meter deep pit presented a danger because climbing down between the wall and the earth to tighten the outer screws is extremely dangerous.
My solution was to place the blue rail and brackets on stones, set the steel wall inside, screw the side poles on, and reach with my hand under the frame to tighten the screws from the outside.
What I used
Item Amount Notes Bestway Hydrium steel wall pool 1 300cm steel wall pool used as a formwork blue bottom rails and brackets multiple laid out to build the frame stones multiple to support rails during assembly Step 5: Sealing gaps around the pool frame
After screwing all the metal support pillars to the back, I sealed the gap under the edge between the concrete and the profiles at the bottom and top with sealant. I do this because we will use the pool as a formwork, placing insulation against the pool and pouring Styrocrete (fluid concrete) outside it. Sealing the openings prevents the liquid concrete from leaking inside and crawling under the liner.
What I used
Item Amount Notes sealant multiple used to seal gaps under the edge and profiles insulation multiple to be placed against the pool Styrocrete fluid concrete to be poured outside the insulation Step 6: Planning underground pipes and pump shed
With the frame installed, I removed the rubber tiles where the pump and filter shed will go 40cm into the ground. Before pouring Styrocrete, underground PVC pipes must be placed and connected to the pool so the pipe openings remain clear. Water pipes and cables will run through these protective pipes to prevent temperature loss in the ground and make it easy to pull new cables or replace leaking pipes later.
What I used
Item Amount Notes rubber tiles multiple removed for the pump shed location PVC pipes multiple run underground to protect water pipes and cables Step 7: Call to action and upcoming episodes
If you think this is a fun project, please leave a like and click the subscribe button so you do not miss any episodes. Eventually, I will also make a compilation episode where you can watch everything all at once, so stay tuned for that.
Step 8: Takeaways
Placing wooden planks over the pool edges prevents point loading and hole collapse.
Stakes set at 10cm height ensure the concrete foundation is completely level.
Concrete takes 24 hours to walk on and 7 days to reach full strength.
Assembling the steel wall on stones in the pit allows safe tightening of outer screws.
Sealing gaps around the frame prevents fluid Styrocrete from leaking under the pool liner.
Running underground PVC pipes protects lines from frost and allows future cable replacements.
Everything I used
| Item | Amount | Notes |
|---|---|---|
| concrete bags | almost two tons | for the foundation plate |
| wooden planks | thick | 6cm thick, placed over the edges to prevent point load |
| stakes | multiple | set at exactly 10cm height for level pouring |
| pool ladder | 1 | already coming in handy |
| liner | 1 | placed in the pool |
| reinforcement | around the bath | for good adhesion |
| brick | 1 | used to smooth high spots on the concrete |
| Bestway Hydrium steel wall pool | 1 | 300cm steel wall pool used as a formwork |
| blue bottom rails and brackets | multiple | laid out to build the frame |
| stones | multiple | to support rails during assembly |
| sealant | multiple | used to seal gaps under the edge and profiles |
| insulation | multiple | to be placed against the pool |
| Styrocrete | fluid concrete | to be poured outside the insulation |
| rubber tiles | multiple | removed for the pump shed location |
| PVC pipes | multiple | run underground to protect water pipes and cables |
Next steps
In the following episodes, we will start on the underground pipes for water lines and power to protect them against frost and prevent temperature loss. A compilation episode will also be made later to view everything at once.
More from Swimming pool heating
- BuildRocket Stove Pool Heater Build and Testing5 August 2023I build and test a rocket stove pool heater using a stainless steel frame and external spiral pipes filled with sand. The setup successfully warms the pool water by about 5 to 6 degrees at filter pump speed.Read the post
- BuildBuilding a DIY Solar Pool Heater13 August 2023I build a solar pool heater using a wooden frame, black paint, 100 meters of flexible PVC hose, copper pipe fittings, and a transparent plastic cover.Read the post
- BuildFormwork, Insulation, and Liner Installation22 October 2023I installed the underground pipes, PIR insulation panels, and the pool liner, and dealt with a torn liner at the end.Read the post